A40 WEST WAY

HTA was commissioned by FM Conway and AECOM to execute the largest Post-Tensioned Special Inspection (PTSI) contract ever undertaken in the UK.

THE BRIEF
HOW WE HELPED
SCOPE OF WORK

Between 2021 and 2022, HTA was commissioned by FM Conway and AECOM to execute the largest Post-Tensioned Special Inspection (PTSI) contract ever undertaken in the UK. The project focused on the critical CS465 structure of the A40 West Way, requiring an exhaustive structural integrity audit to ensure the continued safety of this major London arterial route.

CHALLENGES

The sheer scale and location of the A40 presented monumental logistical hurdles. The investigation required simultaneous coordination across three distinct high-risk environments: live carriageways, internal confined spaces within the structure, and areas above active rail lines. Securing and managing major rail possessions and road closures while operating multiple teams with varying access requirements demanded a sophisticated level of site management and safety protocol.

BOOK A CONSULTATION

image Olympia
What the CLIENT SAID
Quote

Balfour
Beatty

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Quisque pellentesque tristique tristique. In hac habitasse platea dictumst. Nunc consectetur erat sit.

Aenean eros quam, feugiat quis cursus nec, tempus elementum dui. Vivamus condimentum turpis nec feugiat feugiat. Vestibulum placerat diam erat, in euismod eros accumsan a.

Bob Smith
Operations Director
SERVICES
  • Post-Tensioned Special Investigations (PTSI): Comprehensive intrusive testing and structural health monitoring.

  • Confined Space Entry: Internal inspections of the bridge’s box girders and void spaces.

  • Rail & Highway Liaison: Working within strict rail possessions and strategic road closures.

  • Multi-Team Coordination: Managing large-scale site operations over an 18-month duration.

  • Access Solutions: Utilising bespoke access methods for inspection from the carriageway and from beneath the structure.

SOLUTION

HTA successfully delivered this record-breaking contract by deploying a highly organised, multi-disciplinary team capable of working 24/7 during limited possession windows. By integrating our technical expertise in PTSI with expert logistical planning, we provided FM Conway and AECOM with a complete data set of the structure’s condition, ensuring the A40 West Way remains safe for the thousands of vehicles that rely on it daily.

BOOK A CONSULTATION

image Olympia
HTA Round Icon

DO YOU HAVE A PROJECT YOU
WOULD LIKE TO DISCUSS?

 

NEWS & RESOURCES HUB

Explore our guides, essential reads, projects and more...

30 Years old this year
Events
22/02/2026

30 Years old this year

READ MORE
HTA is growing
Blogs
22/02/2026

HTA is growing

READ MORE
Scotland Capital Bridge Scan
Case Studies
22/02/2026

Scotland Capital Bridge Scan

READ MORE
Partners Left
Partners Right